Over the summer, we arranged to have all the parts we needed
manufactured by AMI in Manhattan. When
we came back to school in August, we gathered all the parts and tools we needed
and did a trial build of our Reconfigurable Habitat.
 |
Aaron, Chris, Amy and Adam bolting together wall sections. |
 |
Aaron showing off. We can't take him anywhere. |
 |
Full horizontal configuration in the Foundation Building parking lot on campus. |
 |
A small diameter for the vertical configuration. |
We discovered a couple problems during the build that were
easy to solve but would have nonetheless caused panic if we hadn’t discovered
them until we installed in the Johnson Space Center. One of the problems we found, for example, was
related to our method of connecting the aluminum tubing. We had intended on using internal connectors
for both the horizontal and vertical configurations until we did our trial run
in August.
 |
An internal connector lines up with the end hole of a piece of aluminum tubing and connect a second piece of tubing with the longer, extruding bolt. |
As seen above, the internal connectors need two bolts in
order to connect the two pieces of aluminum tubing. In the vertical configuration, the bolt heads
on the sides of the tubing ran into each other when attached to the piano
hinges. This meant that the hinges couldn't open as widely as they needed to.
In order to adjust for this, we ordered some more of the plate connectors. Even though the plate connectors also require
two bolts, the bolt heads are on a different side of the aluminum tubing, and
do not interfere with the piano hinges’ motion anymore.
 |
A plate connector connects aluminum tubing by lining up with the end holes on two pieces of tubing that are lined up perpendicularly. |
 |
From this top view, one can see that the wall section on the right is connected with an internal connector. The longer bolt of this connector has its bolt head pointing into the other wall section. If both wall sections are made this way, the bolt heads would run into each other and interfere with the hinges' ranges of motion. The wall section on the left is connected with a plate connector instead. |
This is just one example of a small problem we found during
our trial run. We learned during this
experience how important a trial run, or prototype for example, is to the
design process. We thought we had
designed for every little detail, but commonly enough unforeseen problems
exist.
We also worked on several important documents for the
installation trip to Houston, one of which was the installation guide. This was a 30 page document that covered,
step by painstaking step, our recommended process for building the
Reconfigurable Habitat in both configurations, including pictures. The processes described in this guide also
needed to comply with NASA safety regulations. Incidentally, we found during
our own trial run that this structure can be built a number of ways. Although our installation guide covered one
way to build the Reconfigurable Habitat, it is by no means the only way. Other documents we needed were a Hazard
Analysis, as per NASA safety requirements, and a final presentation called a
Test Readiness Review, or a TRR. The TRR was meant just to update the safety
supervisors at JSC of the project and all the precautions needed for the “risks”
to be nullified.
Our trip to Houston began bright and early on September 10th,
and was an exciting one, to say the least.
Barely outside of Manhattan, we hit a large bump and our trailer came unhitched! Sparks were flying as we tried to slow down
without slamming the trailer into the back of our nice motorpool suburban. After we pulled over, we thought the jack on
the trailer was broken and at that time noticed that neither the trailer not
the suburban had an extra tire jack at all. Half of us made a run to get
another lock for the trailer hitch while the other half of us figured out how
to get the broken lock off and the jack working again. We finally got re-hitched and locked and were
back on the road, sure our bad luck had run out.
Instead, somewhere between OKC and Dallas, we blew out a
tire on the trailer! And, of course, as we knew, we had no tire jack. We had to call Highway Patrol to borrow the
nice Patrolman’s tire jack and then drive 30 mph down the Interstate in order
to get to a gas station because the spare tire needed air that badly. The trip overall took us 15-16 hours, instead
of the expected 12. We arrived safely and in good spirits about 11 pm.
Monday morning, trailer in tow, we met Mary and Christie at
JSC. We spent the whole day building
first the horizontal and then the 15-foot vertical configuration.
 |
Aaron, Chris, Adam, Rachel, and Dr. Lease building the horizontal configuration at JSC. |
Tuesday we gave our TRR and presented all of our other
documentation to NASA. This included
both the installation guide and HA, but it also meant all our Solidworks-turned-ProE
files, the CDR, the PDR, a cost analysis, and our recommended for purchase
items. We also turned over all the tools
we used for building, including 850 nuts and bolts (all the same diameter and color
coded according to length), wrenches, tape measures, all the PVC sheeting for
aesthetic covering, cleaners, gloves, etc.
The extra items we bought were pretty extensive.
 |
We gave our TRR presentation to a NASA safety manager in addition to Christie (not pictured) and Mary. |
 |
Just one of our many piles of tools and structure parts we left in JSC for the Flight Deck of the Future department. |
We also mounted a couple monitors into our structure using
universal TV mounts (supplied by NASA) that interfaced with our design and
covered the rest of the open walls with our PVC sheeting and Velcro.
 |
The team with our partial covered vertical configuration, one monitor mounted! |
Overall the trip went really well. Our installed structure looked great, and we
could not have been more proud of ourselves.
The trip back to Kansas went much more smoothly than the way down, and
we are ready for some time to relax. We
have one final design presentation to give to some professors here at K-State
in November, and we are still waiting to hear further feedback from Mary and
Christie about how our Reconfigurable Habitat has fared since we left!
 |
The team with our fully built horizontal configuration, before we took it apart to built the vertical. |
 |
The finished look. This is our vertical configuration with two monitors mounted, all the open wall space covered with PVC sheeting, and a technology station to boot! |